A production expansion can contain several different tax assets: the land, the building, the machines, and parts of the building serving different functions. The new production-property deduction makes those distinctions worth resolving before the return is filed.

What activity will the building actually support, and which portions of its cost qualify?

Notice 2026-16, issued February 20, provides interim guidance for the section 168(n) allowance. A business that makes the required election can deduct 100% of the qualifying property's eligible adjusted basis in the year it is placed in service. Basis means the investment in the property recognized for tax purposes, after required adjustments; it is not automatically the whole project budget. This is a temporary provision for qualifying nonresidential real property, with its own tests. [1][2][3]

The opportunity is substantial. So is the importance of identifying which portion of the project actually qualifies.

Begin with the activity inside the building

The property must be used as an integral part of a qualified production activity. The law covers qualifying manufacturing, production or refining that substantially transforms a product. Here, the narrower term “production” refers to agricultural and chemical production; it does not cover every business process. Manufacturing and refining are separate qualifying routes under the same provision. [1][2]

Office, administrative, lodging, parking, sales, research, software-development and engineering uses raise specific exclusions. The notice also contains allocation rules and a limited exception for buildings with only a small amount of nonqualifying space. A building should not be treated as entirely eligible simply because the business is a manufacturer. [1]

A floor plan annotated by the operating team is a good starting document. Show what happens in each area and connect the space to the production process. Then have the tax team determine the eligible portion and appropriate basis allocation.

The description “warehouse” or “factory” on a fixed-asset list is not a substitute for that work.

Confirm the dates and the taxpayer

The general construction window begins after January 19, 2025 and ends before January 1, 2029. The property generally must be placed in service after July 4, 2025 and before January 1, 2031, in the United States or a U.S. territory. Original use generally must begin with the taxpayer. [1][2]

There is a specified route for some acquired existing property, with restrictions involving prior production use, prior taxpayer use, related parties, and acquisition timing. Buying an existing factory does not automatically satisfy it. [1]

Ownership also matters. A landlord generally cannot qualify solely because a tenant conducts production in the building. The notice provides particular exceptions involving consolidated groups and certain commonly controlled lessors and users. Those exceptions require an ownership analysis; sharing a family name is not enough. [1]

If the operating business and building are held in separate entities, bring the organization chart and lease into the discussion early.

Allocate the cost before estimating the tax effect

Consider a hypothetical project with $2 million of building basis after excluding land and separately classified equipment. Assume a defensible allocation assigns 80% of that basis to qualifying production property and all other requirements are met.

The assumed eligible basis is $1.6 million. At a constant 30% marginal tax benefit, with the full deduction usable immediately, the illustrative tax reduction would be $480,000.

The 80% is an assumption, not an IRS safe harbor or a suggested default. A basis allocation needs support under the applicable rules. Nor does the tax reduction pay for the entire project: the business still finances the building and bears its operating costs.

Loss limitations, owner-level rules, state conformity, and other interactions can change when the benefit produces cash. Compare the actual return across years rather than applying a tax rate to the construction budget and treating the result as available funds.

Plan for the building after the deduction

The statute includes a ten-year change-of-use rule. If covered property stops serving a qualified production activity and shifts to another productive use, the business may have to include an amount based on the earlier deduction in ordinary taxable income. This is called recapture. The notice explains the calculation and related basis adjustments. [1][2]

A business planning to convert part of the property to offices, lease it differently, or change ownership should therefore revisit the election before implementing the change. The deduction creates a recordkeeping responsibility beyond the filing year.

In our view, the right capital-plan comparison includes expected use, financing, tax timing, and the possibility of later changes. A deduction that fits a durable operating plan is easier to evaluate than one dependent on use the business already expects to abandon.

Ask the project team for construction-start support, placed-in-service evidence, plans showing actual functions, cost detail, ownership and lease documents, and the expected use over the next decade. Have the preparer identify the election requirements and any unresolved qualification question. That file turns a broad promise of immediate expensing into a reviewable conclusion about this building.

A building classification needs its own analysis. For the broader purchase decision, the equipment deductions and cash-flow guide helps separate tax eligibility, service-date evidence, and the cash commitment.

A building name does not determine a tax allowance

A warehouse beside a factory and a structure used directly in a qualifying production process can have different facts. Establish the taxpayer, location, actual intended activity, qualifying dates and allocation of costs before extrapolating from an incentive for production property. Land and mixed-use portions need their own analysis rather than being rolled into one building number.

Request plans, project budget, use descriptions, ownership records and service-date evidence. Reconcile the qualifying cost to the total project cost and calculate the effect on later depreciation and cash taxes. If a relevant use or cost allocation is still only an estimate, say so in the planning memo.

Sources & further reading

Consult the cited authority and its date. A linked webpage may have been updated since this article’s historical reference date.

  1. Notice 2026-16: interim qualified production property guidance. Authority date: 2026-02-20.
  2. Public Law 119-21, section 70307. Authority date: 2025-07-04.
  3. IRS Publication 551: Basis of Assets. Revised December 2025.
← Back to all insights